The figures
| Figure | Value |
|---|---|
| Days from the tender notice to the deadline, median | 31 |
| Days from the tender notice to the award notice, median | 104 |
We measured the tender notices on Find a Tender from November 2025 to October 2026: 262 Find a Tender tender notices that gave a deadline. For the time to award: 223 Procurement Act tenders published in the window that already had an award notice by 13 November 2026; slower procurements are still running, so the true median is longer.
The rules
- Above the threshold. Where tenders can be submitted electronically and every tender document is published with the notice, the tendering period must be at least 25 days; it is 30 days if the documents come later or bids can't be sent electronically, and 35 if both (Procurement Act 2023, s.54).
- Shorter periods. The minimum can be 10 days, for example after a qualifying planned procurement notice, in a state of urgency, or for a contract with a non-central government buyer where only preselected suppliers may tender (Procurement Act 2023, s.54; GOV.UK time periods guidance).
- Below the threshold. Deadlines must be reasonable and the same for every supplier (Procurement Act 2023, s.87).
- What the buyer must weigh. In setting a deadline, the buyer must consider the contract's complexity and the need for site visits, among other things (Procurement Act 2023, s.54).
What it means for a firm of 10 to 50 staff
- Decide in the first week. Read the pack, check the conditions of participation and book any site visit. Note the deadline for clarification questions, which comes before the bid deadline.
- Write in weeks two and three. Draft every quality answer against the scoring guidance, then price from the hours in the specification.
- Keep the last days for checking. A buyer may disregard a tender that breaks a procedural rule in the documents (Procurement Act 2023, s.19), so check the format, the word limits and the uploads before you submit.
- Expect a wait after the deadline. The median time from the tender notice to the award notice was 104 days, and slower procurements take longer.
Sources
- Procurement Act 2023, s.54, s.87 and s.19: time limits and procedural requirements.
- GOV.UK time periods guidance.
- UK public cleaning tenders in numbers: the figures on this page, with their method and a free CSV.
Researched and written with AI assistance.
Figures from Find a Tender’s daily notice files and Contracts Finder, Cabinet Office. Contains public sector information licensed under the Open Government Licence v3.0. How every figure was counted.