The figures
| Figure | Value |
|---|---|
| Days from the tender notice to the bid deadline, median | 31 |
| Days from the tender notice to the award notice, median | 104 |
We measured the notices on Find a Tender from November 2025 to October 2026. For the time to award: 223 Procurement Act tenders published in the window that already had an award notice by 13 November 2026; slower procurements are still running, so the true median is longer. For the deadline: 262 Find a Tender tender notices that gave a deadline.
What happens after the deadline, above the threshold
- The buyer assesses the tenders against the award criteria it published.
- You get an assessment summary. In a competitive tendering procedure, every supplier whose tender was assessed must get one before the buyer publishes its contract award notice. It covers the buyer's assessment of your tender and, if different, of the winning one (Procurement Act 2023, s.50).
- The contract award notice and the standstill. The buyer can't sign the contract until a standstill of at least 8 working days has passed, starting on the day the contract award notice is published (Procurement Act 2023, s.51). Weekends and bank holidays in any of the four UK nations don't count, so the contract can be signed from working day 9 (GOV.UK guidance on contract award notices and standstill).
- The contract details notice. Within 30 days of signing, the buyer publishes a contract details notice (Procurement Act 2023, s.53).
The mandatory standstill doesn't apply to a contract awarded under a framework or by reference to a dynamic market, or to a light touch contract, though the buyer can choose a voluntary one of at least 8 working days (Procurement Act 2023, s.51).
Below the threshold
There is no contract award notice and no standstill below the threshold (GOV.UK guidance on contract award notices and standstill). Once it signs a contract that needed a below-threshold tender notice, the buyer must publish a contract details notice as soon as reasonably practicable (Procurement Act 2023, s.87). Ask the buyer for its timetable.
What it means for a firm of 10 to 50 staff
- Plan for a long gap. With a median of 104 days from notice to award, and 31 of those before the deadline, most of the wait typically comes after you submit. Check the tender documents for how long your bid must stay open, and keep your staff plan current.
- Read your assessment summary the day it arrives. The award notice, and the standstill, can follow straight after. If you lost, our guide to feedback and challenges shows what to do within standstill.
- If you win, start planning on the day you hear. Above the threshold, the contract can't be signed until standstill ends, and staff transfers and site set-up take weeks. Our guide to the mobilisation plan has the steps.
- Ask if you hear nothing. A short email to the buyer's contact asking for the expected award date is enough.
Sources
- Procurement Act 2023, s.50, s.51, s.53 and s.87: assessment summaries, standstill and contract details notices.
- GOV.UK guidance on contract award notices and standstill: counting working days, and no standstill below the threshold.
- UK public cleaning tenders in numbers: the figures on this page, with their method and a free CSV.
Researched and written with AI assistance.
Figures from Find a Tender’s daily notice files and Contracts Finder, Cabinet Office. Contains public sector information licensed under the Open Government Licence v3.0. How every figure was counted.