If you lose an above-threshold cleaning tender, read your assessment summary the day it arrives, because the standstill period of at least 8 working days starts when the buyer publishes its contract award notice, which can follow straight after. Use the summary to see where you lost marks, ask the buyer for any further feedback, and raise genuine errors quickly. A court claim must normally start within 30 days of when you knew of the problem, and only a claim started during standstill stops the contract being signed.
This guide is for owners of cleaning firms with 5–50 staff who have lost a public-sector tender in England run under the Procurement Act 2023; rules and fees were checked on 12 October 2026. To avoid the same marks next time, see how to write quality answers.
Key takeaways
- If your tender reached the final assessment, you'll get a summary of your scores, the reasons and the winner's scores before the award notice is published (Procurement Act 2023, s.50; Procurement Regulations 2024, reg. 31).
- Standstill lasts at least 8 working days, counting the day the award notice is published; bank holidays anywhere in the UK don't count (GOV.UK guidance on contract award notices and standstill).
- Further feedback isn't a legal requirement, but GOV.UK guidance says it can be particularly useful for SMEs (GOV.UK guidance on assessment summaries).
- Most claims under the Act must start within 30 days of when you knew, or ought to have known, of the grounds (Procurement Act 2023, s.106).
What you'll receive: the assessment summary
Every supplier that submitted an assessed tender must receive an assessment summary before the contract award notice is published, and all summaries go out at the same time (Procurement Act 2023, s.50; Procurement Regulations 2024, reg. 31). If you lost, yours must include:
- the award criteria, or a summary of each criterion's weight and scoring;
- your score for each criterion, explained by reference to your tender;
- your total score;
- any further reason you weren't awarded the contract, including why you were disqualified if you were;
- the winning tender's scores, with the same explanations.
It doesn't have to compare your tender with the winner's directly (GOV.UK guidance on assessment summaries). The buyer can withhold commercially sensitive details of the winning tender if there's an overriding public interest, but must say so (Procurement Act 2023, s.94).
If you were knocked out at an earlier stage, such as a questionnaire, you're not owed a summary. The buyer should still tell you in writing as soon as reasonably possible, and is advised to use the same feedback structure (GOV.UK guidance on assessment summaries). Below the threshold, there's no contract award notice and no standstill, so ask the buyer directly for your scores (GOV.UK guidance on contract award notices and standstill).
How to read it
Put the summary next to your tender and the published methodology, and check:
| Check | What could be wrong |
|---|---|
| The arithmetic | A score multiplied by the wrong weight, or totals that don't add up |
| The criteria | Marks given or taken away for something the methodology didn't mention |
| The explanations | Comments about content you included, or didn't include, that are plainly wrong |
| The price score | A formula different from the one published |
| Any rejection | A price rejected as abnormally low without you being asked to explain it (Procurement Act 2023, s.19) |
Buyers must assess tenders against the published criteria and methodology (GOV.UK guidance on assessing competitive tenders). A low score you disagree with isn't an error by itself; a score that ignores what you wrote may be.
Standstill: your window to act
The mandatory standstill period is 8 working days beginning with the day the contract award notice is published, and the buyer can't sign the contract during it (Procurement Act 2023, s.51). Publication day is working day one, and weekends and bank holidays in any part of the UK don't count (GOV.UK guidance on contract award notices and standstill).
Some awards have no mandatory standstill, including call-offs under frameworks, contracts under dynamic markets and light touch contracts, though a buyer can choose a voluntary one of at least 8 working days (Procurement Act 2023, s.51).
The contract is held back automatically only if court proceedings start during standstill and the buyer is told (Procurement Act 2023, s.101). A claim issued after standstill ends gets no automatic suspension, even if the contract isn't yet signed (GOV.UK guidance on remedies).
Asking for more feedback
Buyers may add any other information to a summary, and guidance suggests general feedback can help SMEs improve future tenders, though it isn't legally required (GOV.UK guidance on assessment summaries). Ask early in standstill and be specific: "What would have scored a 4 on the staffing question?" gets a better answer than "Why did we lose?"
Then use the answers. Rework weak answers with how to write a cleaning method statement, check your figures with the cleaning bid price calculator, and use who wins public cleaning contracts to see which buyers award to firms your size. Our re-tender forecast shows contracts coming up next.
Challenge routes
- Raise it with the buyer. Set out the error in writing during standstill. If the buyer agrees to extend standstill, it should re-publish the award notice so everyone knows (GOV.UK guidance on remedies).
- The Public Procurement Review Service. It looks into suppliers' concerns about a specific procurement or late payment, if the issue arose within the last 2 years (GOV.UK procurement compliance oversight). Its recommendations aren't binding, it can't force a buyer to delay or suspend an award, and it pauses during standstill and if you start legal action. It aims to respond within 2 months (Public Procurement Review Service scope and remit).
- The court. In England and Wales, claims go to the High Court (Procurement Act 2023, s.100). Before the contract is signed, the court can set aside the decision, order the buyer to act or award damages (Procurement Act 2023, s.103). Damages can include bid costs if you prove the breach caused them (GOV.UK guidance on remedies). Court fees alone are significant: issuing a High Court claim for something other than money costs £663, and a damages claim adds a fee of 5% of the amount claimed between £10,000 and £200,000, or £10,000 above that (HMCTS civil court fees (EX50)). Legal costs come on top, so get a quote from a procurement solicitor before you decide.
Below the threshold, the duties in the Act's below-threshold part can't be enforced through these court remedies, though public law routes such as judicial review may be open (GOV.UK guidance on remedies).
Before you decide to challenge
Ask four questions before you spend money:
- Would fixing the error change the result? If you were 10 points behind and the mistake is worth 2, a claim won't win you the contract.
- Can you prove it? You'll need to show the breach caused your loss (GOV.UK guidance on remedies).
- Is there time? Count standstill and the 30-day limit from the day you received the summary.
- What do you want? A corrected decision, damages, or simply a better explanation for next time.
If you send a pre-action letter or start proceedings while the review service is looking at your case, tell it, because it will pause its work (Public Procurement Review Service scope and remit).
Worked example: counting standstill over a bank holiday
Suppose the contract award notice is published on Tuesday 24 November 2026. St Andrew's Day, Monday 30 November, is a bank holiday in Scotland (GOV.UK bank holidays), so it doesn't count.
| Working day | Date |
|---|---|
| 1 | Tuesday 24 November |
| 4 | Friday 27 November |
| 5 | Tuesday 1 December |
| 8 | Friday 4 December |
| 9: contract can be signed | Monday 7 December |
To keep the contract on hold, you'd need to start proceedings and tell the buyer by Friday 4 December. If you learned of the problem on 24 November, the 30-day limit for most claims ends on Wednesday 23 December (Procurement Act 2023, s.106). Take legal advice before relying on any date.
Frequently asked questions
Will I see the winner's price?
You'll see the winning tender's score and explanation for each criterion, including price, but commercially sensitive details can be withheld (GOV.UK guidance on assessment summaries).
Can the review service overturn the award?
No. It can recommend that a buyer delays, restarts or suspends a procurement, but its recommendations aren't binding (Public Procurement Review Service scope and remit).
Can I challenge a below-threshold award?
Not through the Act's court remedies, which don't cover its below-threshold duties. Public law routes such as judicial review may be open, so take legal advice (GOV.UK guidance on remedies).
What if the procurement started before 24 February 2025?
The Act doesn't apply, and the earlier rules still govern it (PPN 005). Under those rules, standstill started with a standstill letter rather than an award notice (GOV.UK guidance on assessment summaries). Check the legal basis in the notice.
Can I get a copy of the winning tender?
You can ask under freedom of information, and the buyer must normally reply within 20 working days (Freedom of Information Act 2000, s.10). Trade secrets and commercially sensitive parts can be withheld (Freedom of Information Act 2000, s.43).
Can the deadline for a claim be extended?
The court can extend the 30-day limit for a good reason, but not beyond 3 months from when you knew or ought to have known (Procurement Act 2023, s.106).